Building Progress 5: October 2011

October 7, 2011- Exterior rigid foam insulation starting to go in.

4" thick layer of foil-faced polyisocyanurate insulation (R= 26) goes over plywood sheathing.

Pressure-treated plywood furring strips are attached over the polyiso.

Tyvek Drainwrap goes over the furring strips.

Here's a diagram showing the layers in the wall assembly...

October 27 & 31, 2011- fiber cement siding starting to go up


Solid strand woven bamboo flooring in one of the bedrooms....

Kitchen taking shape. 
Ikea cabinets.  Caesarstone countertop.  Kohler Langlade double basin kitchen sink.

Ikea cabinet wizards Tatiana and Rob at work...

Bathroom shower tile.


Laundry room cabinets going in...